The start of the cooperation of the Technical Chamber of Greece/Department of Western Macedonia (TEE/TDM), with the Regional Unit of Grevena was made at the request of the P.E. Grevena in April of 2015, for the formation of a Working Group, which would have the purpose of assessing the condition of the historical stone bridges and religious monuments in the area of Grevena. This proposal was made against the background of extensive torrential phenomena and intense flooding at the time, culminating in the collapse of the “Plaka” bridge in Tzoumerka. The request found a response from the Standing Committees of the TEE/TDM “Culture” and “Anti-earthquake, civil protection and road safety” and from the competent service for promoting the restoration and promotion of the monuments, Ephorate of Antiquities of Grevena. After some time of investigating the possible ways of cooperation of the three above bodies, the initial proposal was successful and in 5-12-2016 a Program Contract was signed with the parties the Region of Western Macedonia/Regional Unit of Grevena, the Ministry of Culture and Sports (through the EFA of Grevena) and the TEE/TDM for the purpose of carrying out the project “Support evaluation of the state of monuments of the Regional Unit of Grevena”, lasting one year and with a total price of 20,000 euros.
The subject of the contract was the evaluation of the bearing capacity of the traditional stone bridges and the Byzantine and post-Byzantine monuments located in P.E. of Grevena. E.F.A. Grevenon chose and indicated for this purpose, seven (7) stone bridges and 32 Byzantine & post-Byzantine temples (22 in the Municipality of Grevena and 10 in the Municipality of Deskatis). In detail, for each monumental construction, the assessment of pathology, damage and remaining bearing capacity was examined in such a way that priorities could be set for the wider project of restoring and highlighting the Byzantine and post-Byzantine monuments of the region. For each monument, the assessment of the bearing capacity was carried out with various checks and autopsies, which will be analyzed in the main body of the work. The project also included a complete photographic capture of the monuments, as well as a recording-identification of the type of interventions that had been carried out to date on these various monuments. End of the obligations of P.S. included the organization of an informative event in Grevena to present the results of the work.
For the execution of the P.S. project, the TEE/TDM formed a scientific project team (STG) consisting of the following qualified engineer members: Eleni Zaravela, Stavroula Papista, Dionysis Andreola, Evangelia Andreadou, Giorgos Liakos, Metaxas Christos, Turtouras Dimitris, Dona Ioannis, Delma Costas, Albani Petros, Koutsonanou Annita, Koutsianou Anastasia, Neveskiotis Haris. O.E. it started its work in June 2015 and finished it in November 2017. During this time, the staffing of the team changed every time and eventually weakened due to the long period of time and undertaken professional obligations. 8 excursions were carried out in the wider area of Grevena for autopsies of the monuments in accessible and inaccessible places, a total of over 2000 km were traveled, over 20 technical meetings were convened. At least 40 monument condition inventory technical report cards were completed, 100 approximately pages of technical reports were compiled, over 1000 photographs were taken.